Sponsors
Project Updates
Click the tabs below for project updates on the Murphy Creek and Tributaries Master Drainageway Plan.
- Schedule
- Meetings
- Reports
- Task
- Anticipated Date
- Status
- Notice to Proceed
- January 31, 2022
- Issued
- Draft Baseline Hydrology Report
- July 2022
- Complete
- Final Hydrology Report
- December 2022
- Complete
- Draft Alternatives Report
- TBD
- Upcoming
- Report
- Date
- Document
- Final Baseline Hydrology Report
- April 19, 2023
Contacts
PROJECT ENGINEERS
Merrick & Company
PROJECT SPONSORS
Mile High Flood District (MHFD)
City of Aurora
Southeast Metro Stormwater Authority (SEMSWA)
Arapahoe County
It is important to us to get feedback throughout this project. Please feel free to submit a question or comment to the project team using this form: