First Creek, an east bank tributary to the South Platte River, originates upstream of Interstate 70 and E470 and generally flows to the northwest. The area upstream of I-70 has been studied several times, but the tributaries to First Creek have not been studied in detail. This study focuses on the tributaries to First Creek upstream of I-70 that have tributary drainage basins greater than 130 acres. The study area encompasses approximately 8.1 square miles and is located within the City of Aurora and unincorporated Arapahoe County. The study is also located within the limits of the Urban Drainage and Flood Control District boundary. The watershed is currently mostly agricultural or open space with some multi- family residential development. Development is anticipated to increase in this area. The change from mostly undeveloped to more urbanized will have a significant effect on the drainage systems within the study area.

study focus

first creek map

Project Goals

The purpose of this project is to provide
HYDROLOGIC ANALYSIS and to develop
alternatives and recommendations for
STORMWATER INFRASTRUCTURE
IMPROVEMENTS
that will be needed as
development occurs.

Key project goals:

  • Clearly define intent of stormwater improvement goals and objectives for future implementation.
  • Inform, guide, and provide expectations to manage development effects on stormwater quality, drainageway stabilization, flood risk, etc.
  • Integrate proposed improvements with realistic location of future trails, open space, traffic master plans, and development planning.
  • Define stream management corridors to provide stormwater conveyance.
  • Develop guidance for future vegetation and provide reference for roughness coefficients for maintenance purposes.

Master Drainageway Plan
First Creek Tributaries Upstream of I-70

Project Background
Context and key factors that shaped the project and its direction.

Project Goals
Defined goals established to guide decision-making and project success.

Sponsors

  • urban drainage flood control district logo
  • aurora logo
  • southeast metro logo
  • arapahoe logo

Project Updates

Click the tabs below for project updates on the First Creek Tributaries
Upstream of I-70 Master Drainageway Plan.

Task:Anticipated Date:Status:

  • Notice to Proceed
    • June 18, 2018
      • Issued
  • Draft Baseline Hydrology Report
    • December 2018
      • Complete
  • Final Hydrology Report
    • February 2019
      • Complete
  • Final Hydrology Report
    • February 2019
      • Complete
  • Final Hydrology Report
    • February 2019
      • Complete
  • Final Hydrology Report
    • February 2019
      • Complete

Meeting:Date:Summary:

  • Kickoff Meeting
    • June 13, 2018
  • Progress Meeting
    • August 30, 2018
  • Progress Meeting
    • January 23, 2019

PUBLIC MEETING
Tuesday, January 21, 2020, 6-7 PM
Beck Center (8000 Telluride St., Aurora, CO 80011) – Aspen Room

Meeting:Date:Document:

  • Final Hydrology Report
    • February 2019
  • Final Alternatives Report
    • November 2019

Contacts

Project Engineers

Merrick & Company

envelope icon Jeanne Boyle, PE, CFM
Project Manager

envelope icon Clare Steninger, PE
Project Engineer

Project Sponsors

Mile High Flood District (MHFD)

envelope icon Teresa Patterson

City of Aurora

envelope icon Sam Scorza

Southeast Metro Stormwater Authority
(SEMSWA)

envelope icon Jessica Traynor

Arapahoe County

envelope icon Sue Liu, PE, CFM

Questions?

It is important to us to get feedback throughout this project. Please feel free to submit a question or comment to the project team using this form:

    By submitting this form, you agree to Merrick’s Privacy Policy and consent to being contacted regarding your inquiry.